Advertisement

Sunday, April 11, 2010

Time and Work method Tips

Important Facts:


1.If A can do a piece of work in n days, then A’s 1 day work=1/n



2.If A’s 1 day’s work=1/n, then A can finish the work in n days.


Ex: If A can do a piece of work in 4 days,then A’s 1 day’s work=1/4.

If A’s 1 day’s work=1/5, then A can finish the work in 5 days


3.If A is thrice as good workman as B,then: Ratio of work done by

A and B =3:1. Ratio of time taken by A and B to finish a work=1:3



4.Definition of Variation: The change in two different variables

follow some definite rule. It said that the two variables vary

directly or inversely.Its notation is X/Y=k, where k is called

constant. This variation is called direct variation. XY=k. This

variation is called inverse variation.


5.Some Pairs of Variables:


i)Number of workers and their wages. If the number of workers

increases, their total wages increase. If the number of days


reduced, there will be less work. If the number of days is

increased, there will be more work. Therefore, here we have

direct proportion or direct variation.


ii)Number workers and days required to do a certain work is an

example of inverse variation. If more men are employed, they

will require fewer days and if there are less number of workers,


more days are required.


iii)There is an inverse proportion between the daily hours of a

work and the days required. If the number of hours is increased,

less number of days are required and if the number of hours is

reduced, more days are required.


6.Some Important Tips:



More Men -Less Days and Conversely More Day-Less Men.

More Men -More Work and Conversely More Work-More Men.

More Days-More Work and Conversely More Work-More Days.

Number of days required to complete the given work=Total work/One

day’s work.


Since the total work is assumed to be one(unit), the number of days

required to complete the given work would be the reciprocal of one

day’s work.

Sometimes, the problems on time and work can be solved using the


proportional rule ((man*days*hours)/work) in another situation.


7.If men is fixed,work is proportional to time. If work is fixed,

then time is inversely proportional to men therefore,


(M1*T1/W1)=(M2*T2/W2)


Problems


1)If 9 men working 6 hours a day can do a work in 88 days. Then 6 men

working 8 hours a day can do it in how many days?


Sol: From the above formula i.e (m1*t1/w1)=(m2*t2/w2)


so (9*6*88/1)=(6*8*d/1)

on solving, d=99 days.


2)If 34 men completed 2/5th of a work in 8 days working 9 hours a day.

How many more man should be engaged to finish the rest of the work in

6 days working 9 hours a day?


Sol: From the above formula i.e (m1*t1/w1)=(m2*t2/w2)

so, (34*8*9/(2/5))=(x*6*9/(3/5))


so x=136 men

number of men to be added to finish the work=136-34=102 men


3)If 5 women or 8 girls can do a work in 84 days. In how many days can

10 women and 5 girls can do the same work?


Sol: Given that 5 women is equal to 8 girls to complete a work

so, 10 women=16 girls.

Therefore 10women +5girls=16girls+5girls=21girls.


8 girls can do a work in 84 days

then 21 girls —————?

answer= (8*84/21)=32days.

Therefore 10 women and 5 girls can a work in 32days


4)Worker A takes 8 hours to do a job. Worker B takes 10hours to do the

same job. How long it take both A & B, working together but independently,


to do the same job?


Sol: A’s one hour work=1/8.

B’s one hour work=1/10

(A+B)’s one hour work=1/8+1/10 =9/40

Both A & B can finish the work in 40/9 days



5)A can finish a work in 18 days and B can do the same work in half the

time taken by A. Then, working together, what part of the same work they

can finish in a day?


Sol: Given that B alone can complete the same work in days=half the time

taken by A=9days

A’s one day work=1/18

B’s one day work=1/9


(A+B)’s one day work=1/18+1/9=1/6


6)A is twice as good a workman as B and together they finish a piece of

work in 18 days.In how many days will A alone finish the work.


Sol: if A takes x days to do a work then

B takes 2x days to do the same work

=>1/x+1/2x=1/18

=>3/2x=1/18


=>x=27 days.

Hence, A alone can finish the work in 27 days.


7)A can do a certain work in 12 days. B is 60% more efficient than A. How

many days does B alone take to do the same job?


Sol: Ratio of time taken by A&B=160:100 =8:5

Suppose B alone takes x days to do the job.

Then, 8:5::12:x


=> 8x=5*12

=> x=15/2 days.


8)A can do a piece of work n 7 days of 9 hours each and B alone can do it

in 6 days of 7 hours each. How long will they take to do it working together

8 2/5 hours a day?


Sol: A can complete the work in (7*9)=63 days

B can complete the work in (6*7)=42 days


=> A’s one hour’s work=1/63 and

B’s one hour work=1/42

(A+B)’s one hour work=1/63+1/42=5/126

Therefore, Both can finish the work in 126/5 hours.

Number of days of 8 2/5 hours each=(126*5/(5*42))=3days



9)A takes twice as much time as B or thrice as much time to finish a piece

of work. Working together they can finish the work in 2 days. B can do the

work alone in ?


Sol: Suppose A,B and C take x,x/2 and x/3 hours respectively finish the

work then 1/x+2/x+3/x=1/2

=> 6/x=1/2

=>x=12


So, B takes 6 hours to finish the work.


10)X can do ¼ of a work in 10 days, Y can do 40% of work in 40 days and Z

can do 1/3 of work in 13 days. Who will complete the work first?


Sol: Whole work will be done by X in 10*4=40 days.

Whole work will be done by Y in (40*100/40)=100 days.

Whole work will be done by Z in (13*3)=39 days

Therefore,Z will complete the work first.



Complex Problems


1)A and B undertake to do a piece of workfor Rs 600.A alone can do it in

6 days while B alone can do it in 8 days. With the help of C, they can finish

it in 3 days, Find the share of each?


Sol: C’s one day’s work=(1/3)-(1/6+1/8)=1/24

Therefore, A:B:C= Ratio of their one day’s work=1/6:1/8:1/24=4:3:1

A’s share=Rs (600*4/8)=300


B’s share= Rs (600*3/8)=225

C’s share=Rs[600-(300+225)]=Rs 75


2)A can do a piece of work in 80 days. He works at it for 10 days & then B alone

finishes the remaining work in 42 days. In how much time will A and B, working

together, finish the work?



Sol: Work done by A in 10 days=10/80=1/8

Remaining work=(1-(1/8))=7/8

Now, work will be done by B in 42 days.

Whole work will be done by B in (42*8/7)=48 days

Therefore, A’s one day’s work=1/80

B’s one day’s work=1/48


(A+B)’s one day’s work=1/80+1/48=8/240=1/30

Hence, both will finish the work in 30 days.


3)P,Q and R are three typists who working simultaneously can type 216 pages

in 4 hours In one hour , R can type as many pages more than Q as Q can type more

than P. During a period of five hours, R can type as many pages as P can

during seven hours. How many pages does each of them type per hour?


Sol:Let the number of pages typed in one hour by P, Q and R be x,y and z


respectively

Then x+y+z=216/4=54 —————1

z-y=y-x => 2y=x+z ———–2

5z=7x => x=5x/7 —————3

Solving 1,2 and 3 we get x=15,y=18, and z=21



4)Ronald and Elan are working on an assignment. Ronald takes 6 hours to

type 32 pages on a computer, while Elan takes 5 hours to type 40 pages.

How much time will they take, working together on two different computers

to type an assignment of 110 pages?


Sol: Number of pages typed by Ronald in one hour=32/6=16/3

Number of pages typed by Elan in one hour=40/5=8

Number of pages typed by both in one hour=((16/3)+8)=40/3

Time taken by both to type 110 pages=110*3/40=8 hours.



5)Two workers A and B are engaged to do a work. A working alone takes 8 hours

more to complete the job than if both working together. If B worked alone,

he would need 4 1/2 hours more to compete the job than they both working

together. What time would they take to do the work together.


Sol: (1/(x+8))+(1/(x+(9/2)))=1/x

=>(1/(x+8))+(2/(2x+9))=1/x

=> x(4x+25)=(x+8)(2x+9)

=> 2×2 =72


=> x2 = 36

=> x=6

Therefore, A and B together can do the work in 6 days.


6)A and B can do a work in12 days, B and C in 15 days, C and A in 20 days.

If A,B and C work together, they will complete the work in how many days?


Sol: (A+B)’s one day’s work=1/12;


(B+C)’s one day’s work=1/15;

(A+C)’s one day’s work=1/20;

Adding we get 2(A+B+C)’s one day’s work=1/12+1/15+1/20=12/60=1/5

(A+B+C)’s one day work=1/10


So, A,B,and C together can complete the work in 10 days.


7)A and B can do a work in 8 days, B and C can do the same wor in 12 days.

A,B and C together can finish it in 6 days. A and C together will do it in

how many days?


Sol: (A+B+C)’s one day’s work=1/6;

(A+B)’s one day’s work=1/8;


(B+C)’s one day’s work=1/12;

(A+C)’s one day’s work=2(A+B+C)’s one day’s work-((A+B)’s one day

work+(B+C)’s one day work)


= (2/6)-(1/8+1/12)

=(1/3)- (5/24)

=3/24

=1/8

So, A and C together will do the work in 8 days.


8)A can do a certain work in the same time in which B and C together can do it.


If A and B together could do it in 10 days and C alone in 50 days, then B alone

could do it in how many days?


Sol: (A+B)’s one day’s work=1/10;

C’s one day’s work=1/50

(A+B+C)’s one day’s work=(1/10+1/50)=6/50=3/25


Also, A’s one day’s work=(B+C)’s one day’s work

From i and ii ,we get :2*(A’s one day’s work)=3/25

=> A’s one day’s work=3/50

B’s one day’s work=(1/10-3/50)


=2/50

=1/25

B alone could complete the work in 25 days.


9) A is thrice as good a workman as B and therefore is able to finish a job

in 60 days less than B. Working together, they can do it in:


Sol: Ratio of times taken by A and B=1:3.

If difference of time is 2 days , B takes 3 days


If difference of time is 60 days, B takes (3*60/2)=90 days

So, A takes 30 days to do the work=1/90

A’s one day’s work=1/30;

B’s one day’s work=1/90;

(A+B)’s one day’s work=1/30+1/90=4/90=2/45


Therefore, A&B together can do the work in 45/2days

Top

10) A can do a piece of work in 80 days. He works at it for 10 days and then

B alone finishes the remaining work in 42 days. In how much time will A&B,

working together, finish the work?


Sol: Work Done by A n 10 days =10/80=1/8

Remaining work =1-1/8=7/8


Now 7/8 work is done by B in 42 days

Whole work will be done by B in 42*8/7= 48 days

=> A’s one day’s work =1/80 and

B’s one day’s work =1/48

(A+B)’s one day’s work = 1/80+1/48 = 8/240 = 1/30


Hence both will finish the work in 30 days.


11) 45 men can complete a work in 16 days. Six days after they started working,

so more men joined them. How many days will they now take to complete the

remaining work?


Sol: M1*D1/W1=M2*D2/W2

=>45*6/(6/16)=75*x/(1-(6/16))

=> x=6 days



12)A is 50% as efficient as B. C does half the work done by A&B together. If

C alone does the work n 40 days, then A,B and C together can do the work in:


Sol: A’s one day’s work:B’s one days work=150:100 =3:2

Let A’s &B’s one day’s work be 3x and 2x days respectively.


Then C’s one day’s work=5x/2

=> 5x/2=1/40

=> x=((1/40)*(2/5))=1/100

A’s one day’s work=3/100

B’s one day’s work=1/50


C’s one day’s work=1/40

So, A,B and C can do the work in 13 1/3 days.


13)A can finish a work in 18 days and B can do the same work in 15 days. B

worked for 10 days and left the job. In how many days A alone can finish the

remaining work?


Sol: B’s 10 day’s work=10/15=2/3


Remaining work=(1-(2/3))=1/3

Now, 1/18 work is done by A in 1 day.

Therefore 1/3 work is done by A in 18*(1/3)=6 days.


14)A can finish a work in 24 days, B n 9 days and C in 12 days. B&C start the

work but are forced to leave after 3 days. The remaining work done by A in:


Sol: (B+C)’s one day’s work=1/9+1/12=7/36


Work done by B & C in 3 days=3*7/36=7/12

Remaining work=1-(7/12)=5/12

Now , 1/24 work is done by A in 1 day.

So, 5/12 work is done by A in 24*5/12=10 days


15)X and Y can do a piece of work n 20 days and 12 days respectively. X started

the work alone and then after 4 days Y joined him till the completion of work.


How long did the work last?


Sol: work done by X in 4 days =4/20 =1/5

Remaining work= 1-1/5 =4/5

(X+Y)’s one day’s work =1/20+1/12 =8/60=2/15

Now, 2/15 work is done by X and Y in one day.

So, 4/5 work will be done by X and Y in 15/2*4/5=6 days


Hence Total time taken =(6+4) days = 10 days


16)A does 4/5 of work in 20 days. He then calls in B and they together finish

the remaining work in 3 days. How long B alone would take to do the whole work?



Sol: Whole work is done by A in 20*5/4=25 days

Now, (1-(4/5)) i.e 1/5 work is done by A& B in days.

Whole work will be done by A& B in 3*5=15 days


=>B’s one day’s work= 1/15-1/25=4/150=2/75

So, B alone would do the work in 75/2= 37 ½ days.


17) A and B can do a piece of work in 45 days and 40 days respectively. They

began to do the work together but A leaves after some days and then B completed

the remaining work n 23 days. The number of days after which A left the work was


Sol: (A+B)’s one day’s work=1/45+1/40=17/360


Work done by B in 23 days=23/40

Remaining work=1-(23/40)=17/40

Now, 17/360 work was done by (A+B) in 1 day.

17/40 work was done by (A+B) in (1*(360/17)*(17/40))= 9 days

So, A left after 9 days.


18)A can do a piece of work in 10 days, B in 15 days. They work for 5 days.


The rest of work finished by C in 2 days. If they get Rs 1500 for the whole

work, the daily wages of B and C are



Sol: Part of work done by A= 5/10=1/2

Part of work done by B=1/3

Part of work done by C=(1-(1/2+1/3))=1/6

A’s share: B’s share: C’s share=1/2:1/3:1/6= 3:2:1


A’s share=(3/6)*1500=750

B’s share=(2/6)*1500=500

C’s share=(1/6)*1500=250

A’s daily wages=750/5=150/-

B’s daily wages=500/5=100/-


C’s daily wages=250/2=125/-

Daily wages of B&C = 100+125=225/-


19)A alone can complete a work in 16 days and B alone can complete the same

in 12 days. Starting with A, they work on alternate days. The total work will

be completed in how many days?


(a) 12 days (b) 13 days (c) 13 5/7 days (d)13 ¾ days


Sol: (A+B)’s 2 days work = 1/16 + 1/12 =7/48


work done in 6 pairs of days =(7/48) * 6 = 7/8

remaining work = 1- 7/8 = 1/8

work done by A on 13th day = 1/16

remaining work = 1/8 – 1/16 = 1/16

on 14th day, it is B’s turn

1/12 work is done by B in 1 day.


1/16 work is done by B in ¾ day.

Total time taken= 13 ¾ days.

So, Answer is: D


20)A,B and C can do a piece of work in 20,30 and 60 days respectively. In how

many days can A do the work if he is assisted by B and C on every third day?



Sol: A’s two day’s work=2/20=1/10


(A+B+C)’s one day’s work=1/20+1/30+1/60=6/60=1/10

Work done in 3 days=(1/10+1/10)=1/5

Now, 1/5 work is done in 3 days

Therefore, Whole work will be done in (3*5)=15 days.


21)Seven men can complete a work in 12 days. They started the work and after

5 days, two men left. In how many days will the work be completed by the


remaining men?


(A) 5 (B) 6 (C ) 7 (D) 8 (E) none


Sol: 7*12 men complete the work in 1 day.

Therefore, 1 man’s 1 day’s work=1/84

7 men’s 5 days work = 5/12

=>remaining work = 1-5/12 = 7/12


5 men’s 1 day’s work = 5/84

5/84 work is don by them in 1 day

7/12 work is done by them in ((84/5) * (7/12)) = 49/5 days = 9 4/5 days.

Ans: E


22).12 men complete a work in 9 days. After they have worked for 6 days, 6 more

men joined them. How many days will they take to complete the remaining work?




(a) 2 days (b) 3 days (c) 4 days (d) 5days


Sol : 1 man’s 1 day work = 1/108

12 men’s 6 days work = 6/9 = 2/3

remaining work = 1 – 2/3 = 1/3

18 men’s 1 days work = 18/108 = 1/6


1/6 work is done by them in 1 day

therefore, 1/3 work is done by them in 6/3 = 2 days.

Ans : A


23).A man, a woman and a boy can complete a job in 3,4 and 12 days respectively.

How many boys must assist 1 man and 1 woman to complete the job in ¼ of a day?



(a). 1 (b). 4 (c). 19 (d). 41


Sol : (1 man + 1 woman)’s 1 days work = 1/3+1/4=7/12


Work done by 1 man and 1 women n 1/4 day=((7/12)*(1/4))=7/48

Remaining work= 1- 7/48= 41/48

Work done by 1 boy in ¼ day= ((1/12)*(1/4)) =1/48

Therefore, Number of boys required= ((41/48)*48)= 41 days

So,Answer: D


24)12 men can complete a piece of work in 4 days, while 15 women can complete


the same work in 4 days. 6 men start working on the job and after working for

2 days, all of them stopped working. How many women should be put on the job

to complete the remaining work, if it is to be completed in 3 days.



(A) 15 (B) 18 (C) 22 (D) data inadequate


Sol: one man’s one day’s work= 1/48

one woman’s one day’s work=1/60


6 men’s 2 day’s work=((6/48)*2)= ¼

Remaining work=3/4

Now, 1/60 work s done in 1 day by 1 woman.

So, ¾ work will be done in 3 days by (60*(3/4)*(1/3))= 15 woman.

So, Answer: A



25)Twelve children take sixteen days to complete a work which can be completed

by 8 adults in 12 days. Sixteen adults left and four children joined them. How

many days will they take to complete the remaining work?



(A) 3 (B) 4 ( C) 6 (D) 8


Sol: one child’s one day work= 1/192;

one adult’s one day’s work= 1/96;


work done in 3 days=((1/96)*16*3)= 1/2

Remaining work= 1 – ½=1/2

(6 adults+ 4 children)’s 1 day’s work= 6/96+4/192= 1/12

1/12 work is done by them in 1 day.

½ work is done by them 12*(1/2)= 6 days


So, Answer= C


26)Sixteen men can complete a work in twelve days. Twenty four children can

complete the same work in 18 days. 12 men and 8 children started working and

after eight days three more children joined them. How many days will they now

take to complete the remaining work?



(A) 2 days (B) 4 days ( C) 6 days (D) 8 days


ol: one man’s one day’s work= 1/192


one child’s one day’s work= 1/432

Work done in 8 days=8*(12/192+ 8/432)=8*(1/16+1/54) =35/54

Remaining work= 1 -35/54= 19/54

(12 men+11 children)’s 1 day’s work= 12/192 + 11/432 = 19/216

Now, 19/216 work is done by them in 1 day.


Therefore, 19/54 work will be done by them in ((216/19)*(19/54))= 4 days

So,Answer: B


27)Twenty-four men can complete a work in 16 days. Thirty- two women can

complete the same work in twenty-four days. Sixteen men and sixteen women

started working and worked for 12 days. How many more men are to be added to

complete the remaining work in 2 days?



(A) 16 men (B) 24 men ( C) 36 men (D) 48 men



Sol: one man’s one day’s work= 1/384

one woman’s one day’s work=1/768

Work done in 12 days= 12*( 16/384 + 16/768) = 12*(3/48)=3/4

Remaining work=1 – ¾=1/4

(16 men+16 women)’s two day’s work =12*( 16/384+16/768)=2/16=1/8


Remaining work = 1/4-1/8 =1/8

1/384 work is done n 1 day by 1 man.

Therefore, 1/8 work will be done in 2 days in 384*(1/8)*(1/2)=24men


28)4 men and 6 women can complete a work in 8 days, while 3 men and 7 women

can complete it in 10 days. In how many days will 10 women complete it?



(A) 35 days (B) 40 days ( C) 45 days (D) 50 days


Sol: Let 1 man’s 1 day’s work =x days and


1 woman’s 1 day’s work=y

Then, 4x+6y=1/8 and 3x+7y=1/10.

Solving these two equations, we get: x=11/400 and y= 1/400

Therefore, 1 woman’s 1 day’s work=1/400

=> 10 women will complete the work in 40 days.


Answer: B


29)One man,3 women and 4 boys can do a piece of work in 96hrs, 2 men and 8 boys

can do it in 80 hrs, 2 men & 3 women can do it in 120hr. 5Men & 12 boys can do

it in?


(A) 39 1/11 hrs (B) 42 7/11 hrs ( C) 43 7/11 days (D) 44hrs


Sol: Let 1 man’s 1 hour’s work=x


1 woman’s 1 hour’s work=y

1 boy’s 1 hour’s work=z

Then, x+3y+4z=1/96 ———–(1)

2x+8z= 1/80 ———-(2)


adding (2) & (3) and subtracting (1)

3x+4z=1/96 ———(4)

From (2) and (4), we get x=1/480

Substituting, we get : y=1/720 and z= 1/960

(5 men+ 12 boy)’s 1 hour’s work=5/480+12/960 =1/96 + 1/80=11/480


Therefore, 5 men and 12 boys can do the work in 480/11 or 43 7/11hours.

So,Answer: C

Friday, March 26, 2010

Find thevalue of X?

What is the value of the variable X in the equation as shown in the figure?

Find  thevalue of X?

Divide by Parts

Divide 110 into two parts so that one will be 150 percent of the other. What are the 2 numbers?

Is A Guilty?

There was a robbery in which a lot of goods were stolen. The robber(s) left in a truck. It is known that : (1) Nobody else could have been involved other than A, B and C. (2) C never commits a crime without A's participation. (3) B does not know how to drive. So, is A innocent or guilty?

Who is in the picture?

Stephen was looking at a photo. Someone asked him, "Whose picture are you looking at?" He replied: "I don't have any brother or sister, but this man's father is my father's son." So, whose picture was Stephen looking at?

Order Finder

Isaac and Albert were excitedly describing the result of the Third Annual International Science Fair Extravaganza in Sweden. There were three contestants, Louis, Rene, and Johannes. Isaac reported that Louis won the fair, while Rene came in second. Albert, on the other hand, reported that Johannes won the fair, while Louis came in second.

In fact, neither Isaac nor Albert had given a correct report of the results of the science fair. Each of them had given one correct statement and one false statement. What was the actual placing of the three contestants?

Bulbs

There are three switches downstairs. Each corresponds to one of the three light bulbs in the attic. You can turn the switches on and off and leave them in any position.
How would you identify which switch corresponds to which light bulb, if you are only allowed one trip upstairs?

Immortal wars

the war is legend and myth
it was started in temples
the three opposing leaders were siblings
by magic blood
one ruled the ocean
other the sky
last the dead
they were in times of ancient
each wants the throne



what and who are the three opposing leaders and what throne are they fighting over?

Friday, March 5, 2010

The 11 Rule

You likely all know the 10 rule (to multiply by 10, just add a 0 behind the number) but do you know the 11 rule? It is as easy! You should be able to do this one in you head for any two digit number. Practice it on paper first!

To multiply any two digit number by 11:

  • For this example we will use 54.
  • Separate the two digits in you mind (5__4).
  • Notice the hole between them!
  • Add the 5 and the 4 together (5+4=9)
  • Put the resulting 9 in the hole 594. That's it! 11 x 54=594

The only thing tricky to remember is that if the result of the addition is greater than 9, you only put the "ones" digit in the hole and carry the "tens" digit from the addition. For example 11 x 57 ... 5__7 ... 5+7=12 ... put the 2 in the hole and add the 1 from the 12 to the 5 in to get 6 for a result of 627 ... 11 x 57 = 627
Practice it on paper first!

Squaring a 2-digit number ending in 8

  1. Choose a 2-digit number ending in 8.
  2. The last digit of the answer is always 4: _ _ _ 4
  3. Multiply the first digit by 6 and add 6 (keep the
    carry): _ _ X _
  4. Multiply the first digit by the next consecutive
    number and add the carry: the product is the first
    two digits: XX _ _.

Example:

  1. If the number is 78:
  2. The last digit of the answer is 4: _ _ _ 4
  3. Multiply the first digit (7) by 6 and add 6 (keep the
    carry): 7 × 6 = 42, 42 + 6 = 48; the next digit of the
    answer is 8 (keep carry 4): _ _ 8 4
  4. Multiply the first digit (7) by the next number (8)
    and add the carry (4):
    7 × 8 = 56, 56 + 4 = 60 (the first two digits): 6 0 _ _
  5. So 78 × 78 = 6084.

See the pattern?

  1. For 38 × 38
  2. The last digit of the answer is 4: _ _ _ 4
  3. Multiply the first digit (3) by 6 and add 6 (keep the
    carry): 3 × 6 = 18, 18 + 6 = 24; the next digit of the
    answer is 4 (keep carry 2): _ _ 4 4
  4. Multiply the first digit (3) by the next number (4)
    and add the carry (2):
    3 × 4 = 12, 12 + 2 = 14 (the first two digits): 1 4 _ _
  5. So 38 × 38 = 1444

Learn the pattern, practice other examples, and you will be a whiz at giving these squares.

Squaring a 2-digit number ending in 7

  1. Choose a 2-digit number ending in 7.
  2. The last digit of the answer is always 9: _ _ _ 9
  3. Multiply the first digit by 4 and add 4
    (keep the carry): _ _ X _
  4. Multiply the first digit by the next consecutive number and
    add the carry: the product is the first two digits:
    XX _ _.

Example:

  1. If the number is 47:
  2. The last digit of the answer is 9: _ _ _ 9
  3. Multiply the first digit (4) by 4 and add 4
    (keep the carry): 4 × 4 = 16, 16 + 4 = 20; the next
    digit of the answer is 0 (keep carry 2): _ _ 0 9
  4. Multiply the first digit (4) by the next number (5)
    and add the carry (2):
    4 × 5 = 20, 20 + 2 = 22 (the first two digits): 2 2 _ _
  5. So 47 × 47 = 2209.

See the pattern?

  1. For 67 × 67
  2. The last digit of the answer is 9: _ _ _ 9
  3. Multiply the first digit (6) by 4 and add 4 (keep the
    carry): 4 × 6 = 24, 24 + 4 = 28; the next digit of the
    answer is 0 (keep carry 2): _ _ 8 9
  4. Multiply the first digit (6) by the next number (7)
    and add the carry (2):
    6 × 7 = 42, 42 + 2 = 44 (the first two digits): 4 4 _ _
  5. So 67 × 67 = 4489.

Squaring a 2-digit number ending in 6

  1. Choose a 2-digit number ending in 6.
  2. Square the second digit (keep the carry): the last digit
    of the answer is always 6: _ _ _ 6
  3. Multiply the first digit by 2 and add the carry
    (keep the carry): _ _ X _
  4. Multiply the first digit by the next consecutive number and
    add the carry: the product is the first two digits:
    XX _ _.

Example:

  1. If the number is 46, square the second digit :
    6 × 6 = 36; the last digit of the answer is 6
    (keep carry 3): _ _ _ 6
  2. Multiply the first digit (4) by 2 and add the carry
    (keep the carry): 2 × 4 = 8, 8 + 3 = 11; the next digit
    of the answer is 1: _ _ 1 6
  3. Multiply the first digit (4) by the next number (5)
    and add the carry: 4 × 5 = 20, 20 + 1 = 21
    (the first two digits): 2 1 _ _
  4. So 46 × 46 = 2116.

See the pattern?

  1. For 76 × 76, square 6 and keep the carry (3):
    6 × 6 = 36; the last digit of the answer is 6: _ _ _ 6
  2. Multiply the first digit (7) by 2 and add the carry:
    2 × 7 = 14, 14 + 3 = 17; the next digit of the answer
    is 7 (keep carry 1): _ _ 7 6
  3. Multiply the first digit (7) by the next number (8)
    and add the carry: 7 × 8 = 56, 56 + 1 = 57
    (the first two digits: 5 7 _ _
  4. So 76 × 76 = 5776.

Share

Twitter Delicious Facebook Digg Stumbleupon Favorites